Schedule

 

Regular visits by our members in Krakow (in their spare time, of course) will take during the reconstruction of car #144. Most of the preliminary engineering work was completed on a voluntary basis by our own members – something we can be proud of. Reconstruction of car #144 will take place in several steps. The following pictures of our last project, car #1023, detail these steps.

 

January 2020:
Preliminary engineering works, first parts specified.

20161028 BW1023 Untergestell 3D Modell

 

July 2020 - December 2020:
New frame manufactured based on original drawings.

20170118 BW1023 RahmenUndUntergestell

 

December 2020:
Car #144 will leave Nuremberg, reconstruction starts.

20170128 BW1023 Untergestell 1281181

 

December 2020 - October 2021:
A new wood car body will be built.

20170922 BW1023 Wagenkasten 05

 

October 2021 – June 2023:
Interior works.

20180723 BW1023 Innendecke IMG 2788

 

March 2022 – July 2023:
Install electric components and wiring.

20180920 BW1023 02 Unterboden Elektrik IMG 3431

 

March 2022 – July 2023:
Install windows, roofing and painting.

20180710 BW1023 Dachbespannung 03 IMG 2660

 

September 2024:
Car #144 returns to Nuremberg. Completion works and return to service.

20181217 BW1023 Ankunft 0051 R